Final paving at the Amelia Island Parkway and Buccaneer Trail roundabout is now set for Saturday, Nov. 7, and may stretch into Sunday, Nov. 8, weather permitting, according to a weekly project update from Nassau County. The Nov. 7–8 schedule is the third announced target for final paving. Nassau County first listed Oct. 10–11, then moved the work to Oct. 24–25 because of the weather forecast. The county's Nov. 1 update says weather impacts last weekend delayed the final friction course again.

Drivers should expect short-term traffic control and flaggers during the weekend work, the county update said.


What's done, what's next


Crews finished several tasks during the week of Oct. 26, according to the county update posted Nov. 1 by communications officer Sabrina Robertson. Final grading of roadside swales and sod placement is complete. The county said FPL completed work on the new light poles, and the old poles have been removed.

Light fixture installation is planned for the week of Nov. 2.

After the final asphalt layer goes down, thermoplastic pavement markings will follow no sooner than 14 days later to allow proper cure time. That puts lane striping no earlier than late November.

Project background

Nassau County commissioners unanimously approved the roundabout construction contract on Dec. 8, 2025, awarding $1,824,936.18 to MAER Construction, according to board meeting minutes. Commissioner Martin made the motion, and Commissioner McCullough seconded it.

The roundabout sits at the junction where the newer Amelia Island Parkway Trail meets the older Amelia Island Trail. In May, all pedestrian, bicycle and vehicle traffic through the intersection was still closed, forcing trail users to detour along South Fletcher Avenue, according to the trail blog. The roundabout and trail have since reopened while finish work continues.

Contact information

Residents with questions about the project can reach project administrator Rafael Castro at KCI Technologies through Nassau County's project page.