Crews started pulling apart Brett's Waterway Cafe in Fernandina Beach in late October after wind delays pushed back the scheduled start.

Workers with Baker Design Build began taking down the 41-year-old building at the foot of Centre Street, peeling away sections of the entryway and roof with an excavator, the Fernandina Beach News-Leader reported Oct. 29. A crowd watched as the work got underway.

The demolition had originally been scheduled for Monday, Oct. 26, but 40 mph wind gusts forced a postponement, the Fernandina Observer reported. Deputy City Manager Glenn Akramoff said at the time that worker safety and environmental protection prompted the delay. Crews could not keep a turbidity barrier in place to prevent sediment from spreading into the Amelia River.

By Oct. 28, the Fernandina Observer confirmed that demolition had begun.

The teardown is not quick. Brett's extends over the river on a deteriorating system of concrete and steel supports. A video inspection beneath the building revealed that some steel beams had fallen, Akramoff told the Observer. That uncertain condition is why contractors planned to work from above, removing small sections rather than bringing down large portions at once.

"It's going to take 20 to 30 days because we're going to go very slow," Akramoff said, according to the Observer.

The restaurant closed Oct. 4, 2025, after 41 years of waterfront dining. In July 2021, the city had declared the building structurally unsafe, citing the active collapse of a concrete double-tee structural member beneath it, the Observer reported. The restaurant's operators challenged the city's actions, and the disagreement over repairs and continued operation stretched over several years.

What comes next at the marina

The demolition is the first visible step in Fernandina Beach's $12.58 million redevelopment of Fernandina Harbor Marina. The City Commission approved the project July 21, awarding a roughly $9.66 million construction contract to Baker Design Build.

The project includes replacing the aging bulkhead, removing more than 60 aging pilings, expanded dredging and construction of a new public pier extending into the Amelia River. The pier will be aligned more closely with Centre Street, opening river views and creating a direct pedestrian connection between downtown and the waterfront.

New floating docks, gangways and fuel distribution facilities are also planned. The marina is expected to remain open during construction, with some boats and services relocated as work progresses.

The city's previously announced construction schedule calls for completion by Dec. 3, 2027.